True island mode. Deterministic power.

On-site generation, a central medium-voltage switchgear lineup and defined load zones — delivering capacity that does not depend on the public grid.

22.41 MVATotal generation @ PF ~0.80
17.93 MWNet deliverable (class)
4 + 4CAT G3616 / G3516
13.8 kV · 60 HzIsland bus

Architecture

From gas engine to rack, on one site

The facility generates its own power with four CAT G3616 and four CAT G3516 gas engines. Their output is collected on a 13.8 kV, 60 Hz bus and distributed through a central medium-voltage switchgear lineup to defined load zones.

Operating in island mode means the site balances generation and load itself. That removes interconnection queues and grid curtailment from the equation and makes delivered capacity predictable over long contract terms — the property long-duration compute needs most.

Capacity is organized into a baseline zone for steady-state loads, a flex zone for higher-density deployments, and reserve headroom for expansion without overbuild.

Architecture in figures

How power reaches your load

From natural gas to the load zone: one site, one medium-voltage bus, three planning zones.

Energy flow · simplified one-line view

From natural gas to compute load — on one site

  1. 1

    Fuel

    Natural gas

    Supplied to the on-site generation plant.

  2. 2

    Generation

    8 gas engine gensets

    4× CAT G3616
    4× CAT G3516

    Reciprocating prime movers, 60 Hz.

  3. 3

    Distribution

    13.8 kV bus

    Central medium-voltage switchgear lineup.

    Installed
    22.41 MVA
    × Power factor
    0.80
    = Net deliverable
    17.93 MW
  4. 4

    Load zones

    • Load ABaseline · 8–10 MW IT
    • Load BFlex, liquid-ready · 6–7 MW IT
    • ReserveHeadroom · ~1–2 MW

Island mode: no connection to the public grid. Generation and load are balanced on site.

Source: Cottleone site specification · Status: November 2026. Simplified view for orientation; single-line diagrams and operating limits are provided in the data room.

Capacity allocation

17.93 MW net, organized in three planning zones

Solid: lower boundLighter: planning rangeHatched: reserve

View as table
ZoneUsePlanning range
Load ABaseline, steady state8–10 MW IT
Load BFlex, higher density, liquid-ready6–7 MW IT
ReserveHeadroom and expansion~1–2 MW
TotalNet deliverable (22.41 MVA × 0.80)17.93 MW

Ranges are planning figures, not guaranteed maxima. The combined allocation of all zones never exceeds 17.93 MW net; deliverable IT load depends on workload mix and cooling design.

Source: Cottleone site specification · Status: November 2026.

Why it matters

Six reasons operators choose island mode

Infrastructure-first delivery: measurable capacity, metered energy and operational control.

True island mode

Off-grid operation reduces dependency on public-grid dynamics and enables controlled delivery planning.

Auditable delivery

Transparent metering supports reliable invoicing and reporting for every stakeholder.

Modular expansion

Capacity scales via standard pods, blocks and pads — without redesigning the site each phase.

Operational governance

Defined access, acceptance and maintenance windows protect stability and availability.

Liquid-ready

A practical path from baseline air cooling to high-density liquid deployments.

Controlled access

Clear access procedures and optional remote hands for predictable multi-tenant operations.

Specification

Site specification

Public summary. Detailed single-line diagrams and operating limits are provided in the data room.

ParameterValueNote
Generation4× CAT G3616 · 4× CAT G3516Gas-fired prime movers
Installed capacity22.41 MVAAt power factor ~0.80
Net deliverable17.93 MWClass figure
Distribution13.8 kV, 60 HzCentral MV switchgear lineup
Load A8–10 MW ITBaseline, immersion / air
Load B6–7 MW ITFlex, liquid-ready
Reserve~1–2 MWHeadroom and expansion

FAQ

Questions buyers ask first

Straight answers for deployment planning, procurement and operations.

What does island mode mean?

The site generates and balances its own power without a connection to the public grid. Delivery is therefore not affected by grid curtailment or interconnection queues.

How is reliability managed?

Through multiple prime movers, defined load zones, reserve headroom and governed maintenance windows.

Can the site expand?

Yes. Capacity is organized in standard blocks, pods and pads so additional phases can be added without redesign.

Review the full technical package

Single-line diagrams, operating limits and commissioning sequence are shared in the data room after verification.